GEOSCIENTIFIC PROGRAMS
Program Number
Operator/Survey
(Location) |
Vessel/
Contractor |
Start Date |
Kms Completed
(Total Planned) |
Comments |
8924-G005-015P
GSI/Labrador 2D Seismic Survey |
M/V GSI Pacific/
Geophysical
Service Inc. |
June 30, 2006 |
3023 CMP Km
(20,671 CMP Km) |
114 CMP Km recorded during reporting
period. |
8924-H032-005E
Husky Oil Operations Limited/Wild Rose 3D seismic survey |
Western Regent/ Western Geco |
July 7, 2006 |
11,848 CMP Km
(11,560 CMP) |
7825 CMP Km recorded during
reporting period. Survey completed July 23, 2006. |
8924-H032-005E
Husky Oil Operations Limited/Fortune 3D Seismic Survey |
Western Regent/
Western Geco |
July 20, 2006 |
0 CMP Km
(24,910 CMP) |
0 CMP Km recorded during reporting
period. |
HIBERNIA DRILLING PROGRAM
Well/Location
(Unique Well Identifier) |
Installation |
Spud Date |
Current Depth
(Projected Total Depth) |
Current Status |
HMDC Hibernia B-16 54W
46� 45� 01.427" N
48� 46� 53.654" W
Licence: PL 1001
(354B164650048454) |
Hibernia Platform
M71 (East Rig) |
May 20, 2006
(Sidetrack date) |
7,090 m
(7,198 m) |
Plugged and abandoned on July 21,
2006 currently conducting rid maintenance. |
HMDC Hibernia B-16 55
46� 45�01.796" N
48� 46� 54.527" W
Licence: PL 1001
(355B164650048450 |
Hibernia Platform
M72 (West Rig) |
--- |
299 m
(300m) |
Conducting rig maintenance. |
TERRA NOVA DRILLING PROGRAM
Well/Location (NAD83)
(Unique Well Identifier) |
Installation |
Spud Date |
Current Depth
(Projected Total Depth) |
Current Status |
Petro-Canada et al Terra Nova
F-88 4
46�27�19.802" N
48�27�41.479" W
Licence: PL 1002
(304F884630048150) |
Henry Goodrich |
May 22, 2006 |
5,617 m
(5,617 m) |
178 mm liner run and cemented �
preparing to run production tree. |
WHITE ROSE DRILLING PROGRAM
Well/Location (NAD83)
(Unique Well Identifier) |
Installation |
Spud Date |
Current Depth
(Projected Total Depth) |
Current Status |
Husky Oil et al White Rose
E-18 6
46� 47" 21.927" N
48� 02 36.529" W
Licence: PL 1006
(306E184650048000) |
GSF Grand Banks |
March 6, 2006 |
1,000 m
(4,668 m) |
Suspended on March 18, 2006 with 406
mm casing set and cemented � To be re-entered at a later date. |
Husky Oil et al White Rose
E-18 5
46� 47� 21.763" N
48� 02� 38.521" W
Licence: PL 1006
(305E184650048000) |
GSF Grand Banks |
March 6, 2006 |
3,402 m
(4,263 m) |
Running 298 x 244mm casing. |
Husky Oil et al White Rose
B-07 7
46 46' 13.49" N
48 00' 38.61" W
Licence: PL 1006
(307B074650048000) |
GSF Grand Banks |
October 12, 2003 |
231m |
914 mm hole drilled, 762 mm
conductor casing set and cemented. |
Husky Oil et al White Rose
B-07 8
46 46� 14.24" N
48 00� 38.16"W
Licence: PL 1006
(308B074650048000) |
GSF Grand Banks |
October 2, 2003 |
3,395 m
(3,395 m) |
Re-entered well on June 23, 2006 �
well terminated (completed) on July 1, 2006. |
Husky Oil et al White Rose
J-22 2
46� 51� 39.62" N
48� 03� 39.93" W
Licence: PL 1006
(302J224700048000) |
GSF Grand Banks |
April 24, 2004 |
1,215 m |
406 mm hole selection drilled, 340
mm casing set and cemented on April 28, 2004 � to be re-entered
at a later date. |
Note: The above status includes
wells that are currently in the drilling or completion phase.
Additional information on the status of various development
wells for the Hibernia, Terra Nova and White Rose projects is
available from the C-NLOPB�s web site under RESOURCE
INFORMATION. Click on Development wells (White Rose Field) for
additional information on the status of White Rose development
wells. |
DELINEATION DRILLING
PROGRAM
Well/Location (NAD83) (Unique Well Identifier) |
Installation |
Spud Date |
Current Depth (Projected Total
Depth) |
Current Status |
Husky Oil et al West Bonne Bay
F-12
46�31� 22.024"N
48�17� 27.216"W
Licence: SDL 1040
(300F124640048150) |
Rowan Gorilla VI |
July 1, 2006 |
3, 430 m(4,631 m) |
Drill 311mm hole |