Natural Resources
December 11, 2009Hebron Partners
Modify Development Concept
The Provincial Government has been notified of a
modification to the development approach for the Hebron
project based on a further engineering analysis by the
operator.
The project operator, ExxonMobil, has informed the
Provincial Government that the original pre-drilling
concept will be eliminated because it is uneconomic and
has significant execution and schedule risks. As a
result of this modification, the fabrication of the
sub-sea drilling template and the components of the
field mooring system and positioning and docking system
will no longer be required. The diligence of the
Provincial Government in negotiating the 2008 Benefits
Agreement ensured that this work would be replaced by
the proponents. The project operator now plans to
complete all drilling from the Gravity-Based Structure.
"We have reviewed the new development concept put
forward by the Hebron proponents, which includes our own
Nalcor Energy, and their rationale for this
modification," said the Honourable Kathy Dunderdale,
Minister of Natural Resources. "We agree with the
decision as we believe it is indeed in the best interest
of the project, and therefore the people of the
province. We had the foresight to ensure that any such
issues were contemplated in the Benefits Agreement and
the replacement value of the work was captured and
protected."
The Provincial Government, through Nalcor Energy,
holds a 4.9 per cent equity interest in the Hebron
project.
Under the 2008 Benefits Agreement, the Hebron
proponents agreed to locate in the province the
fabrication work associated with the sub-sea drilling
template. Based on this commitment, the province has
reached an arrangement with the proponents to replace
the fabrication work with other fabrication work of
equivalent value. This replacement work will be work
that would not otherwise have occurred in the province.
"We are pleased with the arrangement that has been
reached with the operator to replace the fabrication
work," Minister Dunderdale said. "The operator has until
June 30, 2010 to identify the replacement work that will
be undertaken as part of the Hebron construction phase."
Should the operator be unable to identify an
equivalent amount of replacement work by June 30, 2010,
a payment will be made to the province equal in value to
the amount of work not replaced. These funds will then
be used by government for a construction project for the
benefit of the oil and gas industry.
An amendment to the Benefits Agreement will now be
developed by the parties to implement this arrangement.
None of the other commitments in the Benefits Agreement
are affected.
"I am pleased the partners in the Hebron project have
recognized the principle of replacing work in the
province," Minister Dunderdale said. "This means that
the foundation provided in the Benefits Agreement is
strong and resilient, and we look forward to the
development of the project."
For more information on the original Hebron
announcement, please visit
//www.releases.gov.nl.ca/releases/2008/exec/0820n04.htm.
For more information on the project, please go to
//www.hebronproject.com/
- 30 -
Media contact:
Tracy Barron
Director of Communications
Department of Natural Resources
709-729-5282, 690-8241
tracybarron@gov.nl.ca
2009 12 11 1:10 p.m.