Pennecon Energy is doing the refurbishment of the GSF
Grand Banks, owned by a subsidiary of Transocean and currently under a
drilling contract with Husky Energy on the White Rose expansion field.
The multi-million dollar refit contract includes hull coating piping
system renewal, maintenance, equipment overhauls and new equipment
installations. Work is expected to begin in late June or early July and
conclude in October.
"Nalcor Energy is committed to ensuring the Bull Arm
asset is available to maximize the benefits to the province from
large-scale construction and fabrication projects," said the minister.
"This is an important asset for the development of our oil and gas
industry and the advancement of our fabrication capacity."
The refurbishment of the drilling unit will take place
in the FPSO quay and drydock area of the Bull Arm fabrication site.
In August 2008, the Provincial Government announced
the transfer of the Bull Arm Fabrication Site to Nalcor Energy. Bull Arm
is Atlantic Canada�s largest industrial fabrication site. The Bull Arm
site has fully integrated and comprehensive infrastructure to support
construction, fabrication and assembly at its topsides, drydock and
deepwater sites.