GEOSCIENTIFIC PROGRAMS
Program Number
Operator/Survey(Location) |
Vessel/
Contractor |
Start Date |
Kms Completed(Total Planned) |
Comments |
8924-C047-002E
Chevron Canada
Resources Orphan Basin 3D seismic survey |
M/V
Geco Diamond/
WesternGeco Canada |
May
12, 2005 |
151,432 CMP Km
(157,419 CMP Km) |
Acquisition terminated on September 21. |
8924-C047-002E
Chevron Canada
Resources Orphan Basin 3D seismic survey |
M/V
Patriot
WesternGeco Canada |
June 22, 2005 |
117,524 CMP Km
(140,894 CMP Km) |
5,186 CMP km recorded during exporting period.
Acquisition terminated on October 9, 2005 |
8924-C149-002E
ConocoPhillips Canada/South Newfoundland 3D seismic survey |
M/V
Western Neptune/WesternGecoCanada |
June 14, 2005 |
81,572 CMP Km |
Acquisition terminated on September 30. |
8924-G005-014P Geophysical Service Inc./Labrador Shelf 2D seismic survey |
Gulf Pacific/
Geophysical Service Incorporated |
June 17, 2005 |
11,954 KM
(14,225 Km) |
432
Km recorded during reporting period. |
8926-H029-006E
HMDC/Wellsite Survey Hibernia South |
M/V
Maersk Placentia/Fugro Jacques Geosurveys |
September 26, 2005 |
65 Km
(-800Km) |
65
Km recorded during reporting period. |
8924-H032-004E
Husky Oil Operations Limited/Nortern Jeanne d�Arc Basin 3D seismic
survey |
M/V
Western Neptune/Western Geco Canada |
October 3, 2005 |
9,317 CMP Km
(32,560 CMP Km) |
9,317 CMP Km recorded during reporting period. |
HIBERNIA DRILLING PROGRAM
Well/Location
(Unique Well Identifier) |
Installation |
Spud Date |
Current Depth
(Projected Total Depth) |
Current Status |
HMDC Hibernia B-16 52Z
46 45' 02.082" N
48 46' 54.945" W
Licence: PL 1001
(352B164650048451) |
Hibernia Platform
M72 (West Rig) |
March 23, 2005 |
6,950 m
(6,950 m) |
Well drilled to total depth. Preparing to log well. |
HMDC Hibernia B-16 54
46� 45� 01.427"N
48� 46� 53.654"W
(Surface)
Licence: EL 1093
(354B164650048450) |
Hibernia Platform
M71 (East Rig) |
August 1, 2005 |
4,684 m
(8,174 m) |
Drilling 311 mm hole section. |
TERRA NOVA DRILLING PROGRAM
Well/Location
(Unique Well Identifier) |
Installation |
Spud Date |
Current Depth
(Projected Total Depth) |
Current Status |
Petro-Canada et al Terra Nova G-90 6
46� 29� 21.445� N
48� 27� 36.854� W
Licence: PL 1002
(306G904630048150) |
Henry Goodrich |
August 15, 2005 |
3,242 m
(5,943 m) |
Preparing to re-commence drilling operations. |
WHITE ROSE DRILLING PROGRAM
Well/Location
(Unique Well Identifier) |
Installation |
Spud Date |
Current Depth
(Projected Total Depth) |
Current Status |
Husky Oil et al White Rose
B-19
46� 48� 11.20" N
48� 02� 01.43� W
Licence: PL 1006
(300B194650048000) |
Rowan Gorilla VI |
August 22, 2005 |
3,527 m
(3,527 m) |
Well terminated. Rig currently under tow. |
Husky Oil et al White Rose B-07 5
46 46' 14.11" N
48 00' 36.66" W
Licence: SDL 1022(305B074650048000) |
GSF
Grand Banks |
October 6, 2003 |
1,025 m |
508
mm hole drilled, 406 mm surface casing set and cemented. |
Husky Oil et al White Rose B-07 7
46 46' 13.49" N
48 00' 38.61" W
Licence: SDL 1022
(307B074650048000) |
GSF
Grand Banks |
October 12, 2003 |
231m |
914
mm hole drilled, 762 mm conductor casing set and cemented. |
Husky Oil et al White Rose B-07 8
46 46' 14.24" N
48 00' 38.16" W
Licence: SDL 1022
(308B074650048000) |
GSF
Grand Banks |
October 2, 2003 |
231 m |
914
mm hole drilled, 762 mm conductor casing set and cemented. |
Husky Oil et al White Rose J-22 2
46 51' 39.62" N
48 03' 39.93" W
Licence: SDL 1028
(302J224700048000) |
GSF
Grand Banks |
April 24, 2004 |
1,215 m |
406
mm hole section drilled, 340 mm casing set and cemented. |
Husky Oil et al White Rose E-18 2
46 47' 21.414" N
48 02' 41.048" W
Licence: SDL 1024
(302E184650048000) |
GSF
Grand Banks |
September 30, 2004 |
5,390 m
(5,390 m) |
Completion operations finished. Preparing to skid rig to E-18 3. |
Husky Oil et al White Rose E-18 3
46 47' 22.528" N
48 02' 38.052" W
Licence: SDL 1024
(303E184650048000) |
GSF
Grand Banks |
October 8, 2004 |
4,726 m
(4,726 m) |
Suspended at final total depth after performing wellbore clean up and
attempting perforations � to be re-entered for completion at a later
date. |
Note: The above status includes wells that are currently in the drilling
or completion phase. Additional information on the status of various
development wells for the Hibernia, Terra Nova and White Rose projects
is available from the C-NLOPB�s website under RESOURCE INFORMATION.
Click on Development wells (White Rose Field) for additional information
on the status of White Rose development wells. |