NLIS 5
October 5, 2004
(Natural Resources)
The following is being distributed at the
request of the Canada-Newfoundland Offshore Petroleum Board:
Weekly Public Status Report
Oil and Gas Activities Offshore Newfoundland and Labrador
Issued as of: October 4, 2004
(Also available on the Internet - //www.cnopb.nfnet.com)
GEOSCIENTIFIC PROGRAMS
Program Number
Operator/Survey
(Location)
|
Vessel/Contractor |
Start Date |
Kms Completed
(Total Planned)
|
Comments |
8924-C047-001E
Chevron Canada
(Orphan Basin)
|
Veritas Vantage/ Veritas Geophysical |
June 26, 2004 |
4,997
(7,421) |
Phase 1A completed, no more field work
planned for this season. |
8924-G005-013P
GSI
(Labrador)
|
BinHai 512/COSL |
June 29, 2004 |
8,682
(9,712) |
678 km recorded during the week. |
8924-C149-001E
ConocoPhillips
(South Newfoundland)
|
GSI Admiral/GSI |
August 9, 2004 |
1,599
(5,400) |
0 km recorded during week in Newfoundland
& Labrador offshore area. Program suspended. |
HIBERNIA DRILLING PROGRAM
Well/Location
(Unique Well Identifier)
|
Installation |
Spud Date |
Current Depth
(Projected Total Depth) |
Current Status |
HMDC Hibernia B-16 48
46 45' 02.139" N
48 46' 54.862" W
Licence: PL 1001
(348B164650048450)
|
Hibernia Platform
M72 (West Rig) |
August 22, 2004 |
5,163
(6,708 M) |
Drilling 311 mm hole. |
HMDC Hibernia B-16 49/B-16 49Z
46 45' 01.312" N
48 46' 53.654" W
Licence: PL 1001
(349B164650048450)
|
Hibernia Platform
M71 (East Rig) |
August 9, 2004 |
4,005
(4,590 M) |
311 mm hole drilled, 273 mm casing set
and cemented. |
TERRA NOVA DRILLING PROGRAM
Well/Location
(Unique Well Identifier)
|
Installation |
Spud Date |
Current Depth
(Projected Total Depth)
|
Current Status |
Petro-Canada et al Terra Nova
L-98 11/L-98 11Z/L-98 11Y
46 27' 42.166" N
48 29' 51.174" W
Licence: PL 1002
(311L984630048150)
|
Henry Goodrich |
August 9, 2004 |
3,112
(5,339 M)
|
Drilling main hole section. |
WHITE ROSE DRILLING PROGRAM
Well/Location
(Unique Well Identifier)
|
Installation |
Spud Date |
Current Depth
(Projected Total Depth) |
Current Status |
Husky Oil et al White
Rose B-07 1
46 46' 14.31" N
48 00' 38.42" W
Licence: SDL 1022
(300B074650048000)
|
Glomar Grand Banks |
October 18, 2003 |
3,658 M |
Well completed. |
Husky Oil et al White Rose B-07 2
46 46' 14.04" N
48 00' 36.40" W
Licence: SDL 1022
(302B074650048000)
|
Glomar Grand Banks |
October 4, 2003 |
4,610 M |
Well completed. |
Husky Oil et al White Rose B-07 3
46 46' 13.14" N
48 00' 36.92" W
Licence: SDL 1022
(303B074650048000)
|
Glomar Grand Banks |
October 9, 2003 |
970 M |
508 mm hole drilled, 406 mm surface
casing set and cemented. |
Husky Oil et al White Rose B-07 4
46 46' 13.41" N
48 00' 38.35" W
Licence: SDL 1022
(304B074650048000)
|
Glomar Grand Banks |
October 14, 2003 |
3,998 M |
Well completed. |
Husky Oil et al White Rose B-07 5
46 46' 14.11" N
48 00' 36.66" W
Licence: SDL 1022
(305B074650048000)
|
Glomar Grand Banks |
October 6, 2003 |
1,025 M |
508 mm hole drilled, 406 mm surface
casing set and cemented. |
Husky Oil et al White Rose B-07 6
46 46' 13.56" N
48 00' 38.87" W
Licence: SDL 1022
(306B074650048000)
|
Glomar Grand Banks |
October 14, 2003 |
3,719 M |
Well completed. |
Husky Oil et al White Rose B-07 7
46 46' 13.49" N
48 00' 38.61" W
Licence: SDL 1022
(307B074650048000)
|
Glomar Grand Banks |
October 12, 2003 |
231 M |
914 mm hole drilled, 762 mm conductor
casing set and cemented. |
Husky Oil et al White Rose B-07 8
46 46' 14.24" N
48 00' 38.16" W
Licence: SDL 1022
(308B074650048000)
|
Glomar Grand Banks |
October 2, 2003 |
231 M |
914 mm hole drilled, 762 mm conductor
casing set and cemented. |
Husky Oil et al White Rose J-22 1
46 51' 38.81" N
48 03' 40.27" W
Licence: SDL 1028
(300J224700048000)
|
Glomar Grand Banks |
April 15, 2004 |
2,995 M |
Well completed. |
Husky Oil et al White Rose J-22 2
46 51' 39.62" N
48 03' 39.93" W
Licence: SDL 1028
(302J224700048000)
|
Glomar Grand Banks |
April 24, 2004 |
1,215 M |
406 mm hole section drilled, 340 mm
casing set and cemented. |
Husky Oil et al White Rose B-07 9
46 46' 14.521" N
48 00' 41.883" W
Licence: SDL 1022
(309B074650048000)
|
Glomar Grand Banks |
September 22, 2004 |
1,015 M |
508 mm hole drilled, 340 mm surface
casing set and cemented. |
Husky Oil et al White Rose E-18 2
46 47' 21.414" N
48 02' 41.048" W
Licence: SDL 1028
(302E184650048000)
|
Glomar Grand Banks |
September 30, 2004 |
1,011 M |
Running 340 mm surface casing. |
Contact: Canada-Newfoundland Offshore
Petroleum Board, (709) 778-1400.
_______________________________________
Glossary of Petroleum
Terminology
BOP/BOP Stack: Blowout
preventers/blowout preventer stack - an assembly of heavy-duty valves
attached to the wellhead to control well pressure and prevent a blowout.
Casing: Steel pipe set in a well to prevent
the hole from sloughing or caving and to enable formations to be isolated
(there may be several strings of casing in a well, one inside the other).
Cementing: Pumping a liquid slurry of cement,
water and other additives behind a string of casing to isolate formations.
Completion/Completed: The
activities necessary to prepare a well for the production of oil or gas or
the injection of water or gas into the reservoir.
Fish: An
object lost (or stuck) in the wellbore obstructing operations.
Fishing: Operations
to recover fish.
Injecting: Injecting
water or gas into the resevoir for the purpose of maintaining resevoir
pressure, maximizing oil recovery and conserving resources.
Liner: A
length of casing suspended from the base of a previously installed casing
string (a liner does not extend back to the surface of the well).
Logging: Acquisition
of downhole data using tools run in the well, usually on wireline.
Perforate/Perforating: Piercing
the casing and cement using shaped explosive charges to provide a flow path
for formation fluids.
Producing/Production: Flowing
oil and/or gas from a well to the production systems.
Production Tree: An
arrangement of heavy-duty valves and fittings installed on the wellhead to
control flow from the well and/or to facilitate injection operations.
Reaming: An
operation to restore a wellbore to its original diameter (occasionally, a
wellbore will cave in).
Seismic kilometres: The
total number of kilometres of data recorded in a geophysical program.
Shut-in: A
well in which the valves in the production tree have been closed to cease
production or injection operation on a well.
Sidetracking: The
operation of deviating a well around a fish.
Spud: The
initial penetration of the ground or sea floor - the start of the drilling
operation.
Suspension/Suspend: The
temporary cessation of drilling or production operations in a well.
Well Workover: A
program of work performed on an existing well.
Wellbore: The
hole drilled by the drill bit.
Wellhead: Steel
equipment installed at the surface of the well containing an assembly of
heavy duty hangars and seals (the wellhead is used to support the weight of
casing strings hung it and to contain well pressure).
2004 10
05
4:35 p.m. |