NLIS 1 September 3,
2003 (Mines and Energy)
The following is being distributed at the
request of the Canada-Newfoundland Offshore Petroleum
Board:
Weekly Public Status Report Oil
and Gas Activities Offshore Newfoundland and Labrador Issued as of:
September 1, 2003 (Also available at: //www.cnopb.nfnet.com/)
GeoScientific Programs |
Program
Number Operator/Survey (Location) |
Vessel/ Contractor
|
Start Date |
Kms
Completed (Total Planned) |
Comments |
8924-G005-011P GSI/3-D Seismic (N.E. Newfoundland
Shelf) |
GSI
Admiral/GSI |
August 4, 2003 |
10,590 (29,480 CMP) |
2,350
CMP km acquired during the weekending August 31. |
8924-G005-010P GSI/2-D Seismic (N.E. Newfoundland
Shelf) |
Akedemic
Lazarev/SMNG |
August 15, 2003 |
1,708 (4,073) |
706
km acquired during the week ending August 31. |
Hibernia Drilling Program |
Well /
Location (Unique well identifier) |
Installation |
Spud Date |
Current Depth
(Projected Total Depth) |
Current
Status |
HMDC
Hibernia B-16 36 46 45' 01.313" N. 48 46' 54.487"
W Licence: PL 1001 (336B164650048450) |
Hibernia
Platform M71 (East Rig) |
August 14, 2002 |
8,732 M (9,511 M) |
Drilling 216 mm hole section. |
HMDC
Hibernia B16 37 46 45' 01.083" N. 48 46' 53.653" W Licence:
PL 1001 (337B164650048450) |
Hibernia
Platform M71 (East Rig) |
September 2, 2002 |
306 M (- M) |
Suspended. |
HMDC
Hibernia B-16 38 46 45' 01.370" N. 48 46' 53.571"
W Licence: PL 1001 (338B164650048450) |
Hibernia
Platform M71 (East Rig) |
August 22, 2002 |
508 M (- M) |
Suspended. |
HMDC
Hibernia B-16 40 46 45' 02.196" N 48 46' 54.779" W Licence:
PL 1001 (340B164650048450) |
Hibernia
Platform M72 (West Rig) |
December 5, 2002 |
7,225 M (7,258 M) |
Well completed as of August 21, 2003. |
HMDC
Hibernia B-16 41 46 45' 02.024" N 48 46' 54.862" W Licence:
PL 1001 (341B164650048450) |
Hibernia
Platform M72 (West Rig) |
June 23, 2003 |
4,075 M (4,075 M) |
Completing well. |
HMDC
Hibernia B-16 42 46 45' 01.910" N 48 46' 54.695" W Licence:
PL 1001 (342B164650048450) |
Hibernia
Platform M72 (West Rig) |
August 23, 2003 |
303 M (4,931 M) |
Operations
suspended - waiting on equipment repairs - preparing to run 762mmm
conductor casing.
|
Terra Nova Drilling Program |
Well / Location (Unique well
identifier) |
Installation |
Spud Date |
Current Depth (Projected Total
Depth) |
Current Status |
Petro
Canada et al Terra Nova G-90 4 46 29' 21.60" N. 48 27'
37.00" W Licence: PL 1002 (304G904630048150) |
Henry
Goodrich |
January 20,
2002 |
3,890 M (3,890
M) |
Suspended. |
Petro
Canada et al Terra Nova C-69 2Z 46 28' 04.70" N . 48 24'
58.75" W Licence: PL 1002 (302C694630048151) |
Henry
Goodrich |
September 24, 2002
|
4,052 M (4,052 M)
|
Suspended.
|
Petro
Canada et al Terra Nova C-69 3 46 28' 05.42" N 48 00' 59.23
W Licence: Pl 1002 (303C94630048150) |
Henry
Goodrich |
July 31, 2003 |
4,230 M (4,641
M) |
Preparing to drill 216mm hole
section.
|
White Rose
Drilling Program |
Well /
Location (Unique well identifier) |
Installation |
Spud Date |
Current Depth (Projected Total Depth) |
Current Status |
Husky Oil et al White
Rose F-04/F-04 Z 46 43' 17.75" N . 48 00' 44.33" W Licence: EL
1045 (300F04465004800) |
Glomar Grand
Banks |
July
21, 2003 |
1,250 M
(plugged back depth) (3,421 M)
|
Preparing to drill 311mm
sidetrack hole. |
Contact: Canada-Newfoundland
Offshore Petroleum Board, (709) 778-1400.
______________________
Glossary of Petroleum
Terminology
BOP/BOP Stack: Blowout
preventers/blowout preventer stack - an assembly of heavy-duty valves
attached to the wellhead to control well pressure and prevent a
blowout.
Casing: Steel pipe set in a well to
prevent the hole from sloughing or caving and to enable formations to be
isolated (there may be several strings of casing in a well, one inside the
other).
Cementing: Pumping a liquid slurry
of cement, water and other additives behind a string of casing to isolate
formations.
Completion/Completed: The activities
necessary to prepare a well for the production of oil or gas or the
injection of water or gas into the reservoir.
Fish: An object lost (or stuck) in
the wellbore obstructing operations.
Fishing: Operations to recover a
fish.
Injecting: Injecting water or gas
into the reservoir for the purpose of maintaining reservoir pressure,
maximizing oil recovery and conserving resources.
Liner: A length of casing suspended
from the base of a previously installed casing string (a liner does not
extend back to the surface of the well).
Logging: Acquisition of downhole
data using tools run in the well, usually on wireline.
Perforate/Perforating: Piercing the
casing and cement using shaped explosive charges to provide a flow
path for formation fluids
Producing/Production: Flowing oil
and/or gas from a well to the production systems.
Production tree: An arrangement of
heavy-duty valves and fittings installed on the wellhead to control flow
from the well and/or to facilitate injection operations.
Reaming: An operation to restore a
wellbore to its original diameter (occasionally, a wellbore will cave
in).
Seismic kilometers completed: The total number
of kilometers of data recorded in a geophysical program.
Shut-in: A well in which the valves
in the production tree have been closed to cease production or injection
operation on a well.
Sidetracking: The operation of
deviating a well around a fish.
Spud: The initial penetration of the
ground or seafloor - the start of the drilling operation.
Suspension/Suspend: The temporary
cessation of drilling or production operations in a well.
Well workover: A program of
work performed on an existing well.
Wellbore: The hole drilled by the
drill bit.
Wellhead: Steel equipment installed
at the surface of the well containing an assembly of heavy duty hangars
and seals (the wellhead is used to support the weight of casing strings
hung from it and to contain well pressure).
2003 09