NLIS 3
June 11, 2002
(Executive Council)
(Mines and Energy)
(Labrador and Aboriginal Affairs)
Preamble
- The Government of Newfoundland and
Labrador, Inco Limited and the Voisey's Bay Nickel Company Limited have
agreed to a Statement of Principles for the development of the Voisey's
Bay Project.
- This Statement of Principles is the basis
for the preparation of the final, legally binding agreements that will
be entered into by the Parties.
- The preparation of the binding agreements
will commence immediately and are expected to be finalized by September
30, 2002.
Description of the Project
- Inco intends to construct and operate:
- an integrated mine and mill/concentrator
at the Voisey's Bay site;
- a hydrometallurgical demonstration plant
at Argentia; and,
- a hydrometallurgical
nickel/copper/cobalt concentrate processing operation at Argentia.
- An Inco Innovation Centre will be
developed and operated in St. John's in conjunction with Memorial
University.
- The total capital investment required for
the project is estimated at $2.9 billion over the estimated 30 year life
of the project.
- The construction phases of the mine and
mill/concentrator and hydrometallurgical processing plant will create
approximately 1,700 and 3,000 person years of employment, respectively.
- The operating phases of the project will
create the following estimated annual levels of employment:
- mine and mill/concentrator |
400 jobs |
- underground exploration |
85 jobs |
- underground mine operations and
mill/concentrator |
800 jobs |
- research and development program |
200 jobs |
- hydrometallurgical processing
plant |
400 jobs |
- The total direct and indirect employment
benefits are estimated to be 76,000 person years over the estimated 30
year Project life with the provincial GDP impact over the same period
estimated at $11 billion.
Inco's Undertakings
- Infrastructure and Initial Work
Program
Inco will spend a minimum of $55 million
between June 11, 2002 and March 31, 2003, at Voisey's Bay, Argentia and
St. John's. This work program is expected to employ 250 people.
- Hydrometallurgical Process
Research and Development
Site development at Argentia will begin
immediately and continue until design, engineering and construction of the
hydrometallurgical demonstration plant commences in 2004. This plant is
scheduled to be operational in 2006 and employ approximately 200 people.
Total costs for the research and development program at Argentia are
estimated to be $130 million.
Inco will provide annual progress reports
to government on the results of its research and development program
containing sufficient documentation for government to assess the success
of this program.
- Mine and Mill/Concentrator
Processing Plant
Construction is scheduled to begin in 2003
and be completed in 2006 at a cost of $710 million. The capacity of the
plant will be 6,000 tonnes of ore per day. Construction of the plant will
generate approximately 1,700 person years of employment and 400 people
will be employed during operations.
The initial phase will be an advanced
surface exploration program beginning in 2002 with expected completion in
2006 at a cost of $20 million. This phase will employ up to 85 people.
Subsequent underground exploration will employ 85 people at an estimated
cost of $75 million.
- Underground Mine Development and
Mill/Concentrator Expansion
Upon successful completion of an
underground exploration program, Inco will commence underground mine
development which will require an expansion of the mill/concentrator. The
total cost of this program is estimated to be $750 million and will employ
approximately 800 people during operations.
- Hydrometallurgical Processing Plant
Inco will construct a commercial processing
plant in the province capable of producing 110 million pounds of nickel
annually.
By December 31, 2008, Inco will provide
government with its decision to either:
(A) Construct
a commercial hydrometallurgical processing plant in Argentia.
The capital cost is expected to be about
$800 million and construction of the plant will create approximately 3,000
person years of employment. Once in operation, the plant will employ
approximately 400 people.
OR
(B) Construct
a commercial hydrometallurgical nickel matte processing plant or other
such plant using proven, state-of-the-art technology to produce a finished
nickel product.
The capital cost of such a plant is
expected to be about $670 million. Construction of the plant will create
approximately 2,500 person years of employment. Once in operation, the
plant will employ approximately 350 people.
Inco's decision will be supported by (i) a
feasibility study; and (ii) an implementation plan and schedule for
engineering and construction which will confirm that the commercial
processing plant will be completed by December 31, 2011.
Government will either accept Inco's
decision or engage a mutually acceptable third-party engineering firm and
financial expert to review the decision. Government and Inco will accept
the determination made by such experts.
- Guarantee of Concentrate Replacement
Inco guarantees that it will commence
replacement of the concentrate shipped out of the province prior to the
cessation of mining operations at Voisey's Bay .
Inco acknowledges that failure to meet this
contractual obligation will cause the province and the economy of the
province substantial loss. Consequently, the government will be entitled
to claim damages for losses to the province and to the provincial economy.
An Inco Innovation Centre will be developed
and operated in conjunction with Memorial University. The Centre will
focus on education and research in mineral exploration, mining and
metallurgical processing. Inco will spend $10 million on the facility and
provide an annual endowment of $1 million over 10 years. Work will
commence in 2002 with a target completion in 2004.
- Industrial and Employment Benefits
Inco and the government will conclude an
Industrial and Employment Benefits Agreement which will cover:
(a) Full and Fair
Opportunity |
(e) Engineering |
(b) First Consideration
- Procurement |
(f)
Construction/Fabrication Facilities |
(c) First Consideration
- Training and Employment |
(g) Inco's Adjacency
Principle |
(d) Supplier
Participation |
(h) Air and Marine
Operations |
Inco has negotiated and will enter into
Impacts and Benefits Agreements with the Labrador Inuit Association and
the Innu Nation. These agreements contain provisions relating to
employment and business opportunities.
Inco and the province will reach an
agreement which is intended to maximize the allocation of corporate income
tax to the province.
In the event that Inco is prevented from
performing any of its obligations under the Statement of Principles by
reason of one or more events of Force Majeure ( ie. natural disasters,
acts of war, labour disputes) the dates for completion of Inco's
obligations may be extended for a reasonable period of time.
Government's Undertakings
The government will enter into the
following agreements with the Labrador Inuit Association and the Innu
Nation: (i) Interim Measures Agreements that embody the Voisey's Bay
chapter in the respective land claims agreements, and (ii) an
Environmental Management Agreement.
- Electrical Rates and Provision of Power
Newfoundland and Labrador Hydro will charge
the island industrial rate (or some lower rate that may be provided to
customers in similar circumstances) for the demonstration and commercial
processing plants.
The government will issue a mining lease
that will establish an initial annual production rate of 2.2 million
tonnes of ore and increasing to 5.5 million tonnes of ore when underground
mining operations commence.
The government will issue an Exemption
Order allowing Inco to ship out of the province up to 355,000 tonnes of
nickel in concentrate.
Inco will not be permitted to ship any
concentrate out of the province until the demonstration plant is
operational and ready to test.
Inco's right to ship concentrate will be
suspended if:
(a) Inco has not delivered to the
government its decision on the commercial processing plant by December 31,
2008.
(b) Inco is not proceeding diligently with
the engineering and construction of the commercial processing plant
scheduled for completion by December 31, 2011. Progress will be determined
by an independent third party by December 31, 2009, and December 31, 2010.
During the commissioning and ramp-up of the
commercial processing plant, government will permit Inco to ship out an
additional fixed amount of nickel in concentrate containing up to 85,000
tonnes of nickel.
If the decision is taken to construct a
nickel matte processing plant or other plant:
(a) Government will allow Inco to ship
all nickel in concentrate from the province provided that it will be
returned for final processing at a rate that will enable the nickel
matte processing plant to match Voisey's Bay mill/concentrator output.
(b) Inco's right to ship nickel out of the province will be suspended
during periods that the nickel matte processing plant is not operating,
other than for routine maintenance and vacation shutdown.
Inco will be permitted to ship out of the
province all copper concentrate until such time as additional copper
reserves are discovered to permit commercial copper processing in the
Province.
Should government unnecessarily delay the
project by not issuing timely approvals, then Inco's right to ship
concentrate will be extended. This may result in the Project being
extended or additional shipment volumes being granted to Inco.
Government commits not to change
legislation or regulations that would affect the project unless these
changes are of general application.
Government will issue a Special Project
Order under the Labour Relations Act to ensure a stable labour
relations environment for the construction phases of the project.
In return for Inco's commitment to allocate
corporate income tax to the province, government will provide that the
corporate income tax rate will be the lower of the "all provinces
average" rate or the provincial income tax rate and will indemnify
Inco against double taxation.
Government will introduce changes to the Mining
and Mineral Rights Tax Act to limit the 10-year tax holiday and make
other changes designed to ensure a competitive mining tax regime.
Other
- Approval by House of Assembly
Government will seek to obtain approval for
the Statement of Principles in the House of Assembly.
Government and Inco agree that the Binding
Agreements will be governed by the laws of the Province and the federal
laws of Canada and to accept the jurisdiction of the courts of the
Province.
The following are required before the
Binding Agreements are effective:
- passage into law of necessary changes to
the Mining and Mineral Rights Tax Act;
- completion of an Environmental
Management Agreement;
- completion of required aboriginal
agreements, including the Impacts and Benefits Agreements and the
Voisey's Bay chapters in the respective land claims agreements;
- issuance of a mining lease;
- receipt of the Harmful Alteration,
Disruption or Destruction of Fish Habitat (HADD) authorization from
DFO, and;
- arrangement of suitable financing by
Inco.
Statement of Principles
Voisey�s Bay Project
PREAMBLE
1. Discussions between
the Government of Newfoundland and Labrador (the "Government")
and Inco Limited and Voisey�s Bay Nickel Company Limited (collectively
the "Proponent" as defined in Schedule A hereto) have resulted
in the following Statement of Principles for the development of the
Voisey's Bay Project as described below (the "Project").
All dollar amounts
referred to in the Statement of Principles are Canadian dollars. All
employment levels, economic and related benefits and costs of facilities
referred to in the Statement of Principles are current estimates.
2. The Statement of
Principles is not intended to and does not create any legally binding
rights or obligations between the parties. The parties will use their
best efforts to finalize mutually acceptable definitive agreements (the
"Binding Agreements") embodying the Statement of Principles as
expeditiously as possible and in any event by September 30, 2002,
subject to paragraph 47.
3. The principal
conditions to be met in order for the Proponent to proceed with the
Project are: (a) the passage into law of any changes to the Mining and
Mineral Rights Tax Act contemplated by the Statement of Principles, (b)
the completion of an Environmental Management Agreement, (c) the
completion of required aboriginal agreements, including Impacts and
Benefits Agreements and the Voisey's Bay chapter in the respective land
claims agreements or other interim arrangements, (d) the issuance of a
mining lease from the Department of Mines and Energy, (e) the receipt of
the Harmful Alteration, Disruption or Destruction of Fish Habitat
authorization from Fisheries and Oceans Canada, and (f) the arrangement
of suitable financing by the Proponent to enable the Project to be
developed on a financially prudent basis.
DESCRIPTION OF THE PROJECT
4. Commencement of the
Project will occur in 2002 with site mobilization work in Voisey's Bay,
site preparation work at Argentia, and commencement of the development
of an Inco Innovation Centre in St. John's.
5. The Proponent intends
to construct an integrated mine and mill/concentrator processing plant
at the Voisey's Bay site in Labrador that will process ore from the
Voisey�s Bay deposits and a hydrometallurgical nickel/copper/cobalt
processing operation at Argentia that will process the
nickel/copper/cobalt concentrate from the mill/concentrator processing
plant at the Voisey's Bay site to a finished nickel product and be
capable of processing concentrate and intermediate feeds containing
nickel from other sources around the world. This would give the
hydrometallurgical processing plant the capability of operating well
beyond the life of the Voisey�s Bay deposits.
6. An Inco Innovation
Centre will be developed and operated in St. John's in conjunction with
Memorial University of Newfoundland. The Inco Innovation Centre's focus
will be on education and research in mineral exploration, mining and
metallurgical processing.
7. The projected
aggregate capital investment in these and related facilities is
estimated to be $2.9 billion over the estimated 30-year life of the
Project, including sustaining capital expenditures. The Proponent will
prepare comprehensive bankable feasibility studies and, based upon those
studies, the Project capital and operating costs and schedule will be
finalized. A phased approach to development will be used that will
include a significant research and development program to confirm and
demonstrate the technological and commercial application of
hydrometallurgical technology to sulphide concentrates and will include
a demonstration plant to be constructed at Argentia.
8. The Project will
create significant employment opportunities in the Province of
Newfoundland and Labrador (the "Province"). The construction
phases of the mine and mill/concentrator processing plant and the
hydrometallurgical processing plant will create 1,700 and 3,000
person-years of employment, respectively.
During the various operating phases, the Project will create the
following estimated employment levels: mine and mill/concentrator
processing plant � 400 people; research and development program �
200 people; underground exploration � 85 people; underground mine
operations � 800 people; and hydrometallurgical processing plant �
400 people.
9. The total employment
benefits from the Project are estimated to be 76,000 direct and indirect
person-years over the estimated 30-year life of the Project. Provincial
GDP impact over the same period is estimated to be $11 billion.
UNDERTAKINGS
10. The following
undertakings by the Proponent, together with those of the Government,
provide the framework for the proposed development of the Project.
UNDERTAKINGS BY THE PROPONENT
11. The Proponent is
committed to developing the Project in a manner which provides full and
fair benefits to the people of the Province; has a solid business
footing; provides for a reasonable return to its shareholders;
recognizes metals market conditions; can be reasonably and prudently
financed and can be completed as intended. The Proponent will use its
best efforts to obtain the required financing for the Project in
a timely manner. Comprehensive bankable feasibility studies, as referred
to above in paragraph 7, will be prepared which must reflect and
successfully meet these objectives and the undertakings by the Proponent
and the Government contained in the Statement of Principles. The
Proponent's objective is to have a world-class, efficient operation
which will reflect appropriate employment levels, productivity
requirements and other relevant factors.
Infrastructure and Initial
Work Program
12. Commencing in 2002,
the Proponent will undertake site mobilization at Voisey's Bay,
including the establishment of a construction camp, initiation of work
on temporary port facilities, and construction of access roads. At
Argentia, in 2002, the Proponent will complete lease arrangements for
the property and undertake site preparation, including demolition,
fencing, security and signage. The Proponent will also construct a
warehouse building and establish staging areas and lay down areas in
support of Labrador activities and establish a project office and
information centre. Site selection, architectural design and engineering
work for the Inco Innovation Centre in St. John's will also be
undertaken in 2002 with target completion of the Inco Innovation Centre
in 2004. This infrastructure and initial work program, in aggregate, is
expected to employ approximately 250 persons. The Proponent will spend a
minimum of $55 million on this program in the Province by March 31,
2003.
Hydrometallurgical Process
Research and Development
13. Commencing in 2002
with infrastructure development, the Proponent will initiate a
hydrometallurgical process research and development program which will
include the construction and operation of a demonstration plant at
Argentia, at an estimated cost of $130 million. The research and
development program will include the evaluation of chemical engineering
sub-processes for the hydrometallurgical process as well as the
mechanical equipment design for this demonstration plant. The
demonstration plant, scheduled to be operational in 2006, will be used
to establish the commercial, technical and economic feasibility of the
hydrometallurgical process technology for the Voisey�s Bay
nickel/copper/cobalt concentrate. The Proponent will ship
nickel/copper/cobalt concentrate from the Voisey's Bay mine and
mill/concentrator processing plant to the demonstration plant following
successful start up of the mine and mill/concentrator processing plant.
14. The Proponent will
provide an annual confidential progress report to the Government on the
results of its research and development efforts on hydrometallurgical
process technology containing sufficient documentation to enable the
Government to evaluate the Proponent�s progress in developing the
hydrometallurgical process technology.
15. Site development for
the demonstration plant at Argentia will begin in 2002. Following the
initial development activities in late 2002 and early 2003, the
Proponent will continue to develop the site in preparation for the
demonstration plant and ultimately the commercial processing plant. The
initiatives in support of this presence will include operation of an
information centre, preparation of environmental baseline studies and
continued upgrading or replacement of utility services required for the
demonstration plant and maintaining staging areas. Additionally, cleanup
and civil works on the larger area of the Argentia peninsula will be
initiated. This will consist of demolition, grading and earthworks
construction.
16. The Proponent will
explore business opportunities for the ongoing utilization of the
demonstration plant facilities for the evaluation of other concentrates
and intermediate feeds upon completion of the Voisey's Bay
hydrometallurgical research and development program referred to in
paragraph 13.
Mine and Mill/Concentrator
Processing Plant
17. Construction of an
open pit mine and mill/concentrator processing plant at Voisey's Bay,
capable of processing 6,000 tonnes of ore per day, is scheduled to begin
in 2003. These facilities are estimated to require 3 years to construct
at a cost of approximately $710 million. The open pit mine and
mill/concentrator processing plant will generate approximately 1,700
person-years of employment during the construction period and will
employ approximately 400 people in operations. The mill/concentrator
processing plant will produce two separate concentrates: a copper
concentrate that will be sold on the open market and a
nickel/copper/cobalt concentrate that will be processed initially at the
Proponent's operations in Ontario and Manitoba and subsequently at the
commercial hydrometallurgical processing plant at Argentia. The
Proponent will not ship any nickel/copper/cobalt concentrate out of the
Province in accordance with the Exemption Order referred to in paragraph
37 until the demonstration plant referred to in paragraph 13 is
operational and ready to test nickel/copper/cobalt concentrate.
Underground Exploration
18. The Proponent will
undertake an underground exploration program at an estimated cost of $95
million, which will employ approximately 85 people. The objective of
this underground exploration program will be to confirm underground
mineable reserves and develop a mining plan. The initial phase of this
exploration program will be an advanced surface program at an estimated
cost of $20 million that will start in 2002 with target completion in
2006. Subsequent underground exploration will be scheduled to
ensure that sufficient ore is available to sustain full operation of the
mill/concentrator processing plant during the transition from the open
pit operations to full underground mining operations.
Underground Mine
Development and Mill/Concentrator Expansion
19. Subject to completion
of a successful underground exploration program, as part of the
long-term plan for the Project, the Proponent will commence underground
mine development, which will include a mill/concentrator processing
plant expansion, to provide sufficient ore to sustain operation of the
mine and mill/concentrator processing plant. This program is currently
estimated to cost approximately $750 million. The underground mining
operation will result in the employment of 800 people.
20. The Proponent will
use the most efficient and cost-effective mining techniques which are
intended to include state-of-the-art, automated mining technologies.
These technologies will be aimed at lowering operating costs and
extending the Project life.
Hydrometallurgical Processing
Plant
21. The Proponent is
committed to processing the Voisey's Bay nickel/copper/cobalt
concentrate in the Province and to maximizing long-term benefits for the
people of the Province. Consequently, the Proponent will use its best
efforts to develop a technically and economically viable
hydrometallurgical process technology. Upon successful development of
the technology, the Proponent will construct a commercial
hydrometallurgical processing plant in the Province for the
nickel/copper/cobalt concentrate. This plant will have the annual
capacity to produce approximately 110 million lbs of cathode nickel, 5
million lbs of cobalt product and 15 million lbs of copper revert.
Employment during the 3-year construction period will be approximately
3,000 person-years with approximately 400 persons being employed during
operations. The capital cost for this plant is expected to be
approximately $800 million.
22. In the unlikely event
that the Proponent's proposed hydrometallurgical process technology for
the Voisey's Bay nickel/copper/cobalt concentrate is not technologically
or economically feasible, the Proponent will construct a commercial
hydrometallurgical nickel matte processing facility or other facility
incorporating a proven, state-of-the-art technology to produce a
finished nickel product. Such a facility will have the same annual
finished nickel capacity as the hydrometallurgical processing plant as
described in paragraph 21. The capital cost of such a facility is
estimated to be $670 million and will create approximately 2,500
person-years of employment during construction and will employ
approximately 350 people.
23. By no later than
December 31, 2008, the Proponent will provide the Government with its
decision as to whether it will proceed with the engineering and
construction of either the hydrometallurgical processing plant
contemplated by paragraph 21 or such other facility referred to in
paragraph 22. This decision will be supported by a feasibility study
that will include the technical and economic evaluations that are the
basis for the Proponent�s decision. The Proponent will keep the
Government informed of its progress in reaching this decision so as to
enable (1) the Government to determine whether the experts referred to
below will be required, and (2) the Proponent to meet the December 31,
2008 date referred to herein. The Government will either accept the
Proponent�s decision or, prior to December 31, 2008, engage a mutually
acceptable, recognized third party engineering firm and a mutually
acceptable, recognized third party financial expert to review the
Proponent�s decision and make a determination with respect to such
decision. The Government and the Proponent will accept the determination
made by such experts with respect to which facility the Proponent will
construct. By no later than December 31, 2008, the Proponent will also
provide the Government with an implementation plan (reflecting the
determination made by such experts, if applicable) that provides the
schedule for the completion of the engineering work for, and the
construction of, the selected facility. This facility is to be completed
no later than December 31, 2011. The Proponent will proceed diligently
to complete the detailed engineering for, and construction of, the
selected facility.
24. The Proponent's
objective is to operate the hydrometallurgical processing plant for the
Voisey's Bay nickel/copper/cobalt concentrate, the hydrometallurgical
nickel matte processing facility or other facility beyond the life of
the eventual Voisey's Bay mining operations. Accordingly, the Proponent
will explore technically and economically feasible opportunities for
plant expansion and to secure opportunities to supply the plant with
additional feed from around the world to fully utilize the large capital
investment in the processing facilities in the Province.
Guarantee of Concentrate
Replacement
25. In consideration of
the Government granting the Exemption Orders referred to in paragraphs
37, 38, 39 and 40, the Proponent guarantees that it will, prior to the
cessation of mining operations for the Project, commence shipping into
the Province nickel and cobalt concentrate or other form (from
one or more sources worldwide, other than the Project) for processing in
the Province. The quantities of such nickel and cobalt to be shipped
into the Province will be at levels sufficient to enable either the
hydrometallurgical processing plant contemplated by paragraph 21 or such
other facility referred to in paragraph 22 to operate at no less than 50
per cent of the design capacity of such plant or other facility. These
shipments will continue at least until such time as they total the
amount of nickel and cobalt in concentrate or other form that was
shipped from the Province under the terms of the applicable Exemption
Order(s).
The Proponent acknowledges that, if it does not meet its contractual
obligations under this paragraph 25 except for one or more events of
Force Majeure (as defined in Schedule A hereto), (1) the Province and
the economy of the Province will suffer substantial loss if such nickel
and cobalt concentrate or other form is not shipped into and processed
in the Province, and (2) damages are not an adequate remedy for such
breach. However, in the event that damages are awarded, the Government
will be entitled to claim damages for breach of contract to reflect such
losses to the Province and the economy of the Province for the failure
to process such concentrate or other form in the Province and the
Proponent expressly waives any right to claim or argue that the
Government cannot pursue any such suit against the Proponent.
Inco Innovation Centre
26. The Proponent will
establish an Inco Innovation Centre to be developed and operated in
conjunction with Memorial University of Newfoundland. Work on the Inco
Innovation Centre will commence in 2002 with target completion in 2004.
The Proponent will spend $10 million on the Inco Innovation
Centre and provide an annual endowment of $1 million per year
over a 10-year period to cover operational costs. The Inco Innovation
Centre's focus will be on education and research in mineral exploration,
mining and metallurgical processing. It will provide world-class
education, research and training related to the mining industry to 50-60
students per year engaged in Bachelors, Masters and Doctorate level
programs.
Industrial and Employment
Benefits
27. The Proponent will
conclude an Industrial and Employment Benefits Agreement with the Government
for the employment of members of the provincial labour force and for
providing manufacturers, consultants, contractors and service companies
in the Province with a full and fair opportunity to compete for the
supply of goods and services for the Project. The Proponent will detail
plans acceptable to the Government for monitoring and reporting, on a
regular basis, on the efforts of both itself and its contractors in
maximizing benefits to the Province. This Industrial and Employment
Benefits Agreement will include the Proponent's policies which address
principles of full and fair opportunity in procurement from companies in
the Province as well as training and employment of residents of the
Province. These principles and the Industrial and Employment Benefits
Agreement will recognize the Impacts and Benefits
Agreements (IBAs) with the Labrador Inuit Association and Innu Nation
and, pursuant to these IBAs, the Proponent will encourage the formation
of joint ventures or other forms of cooperative business arrangements
between aboriginal people or firms and other businesses in the
Province.
These principles and the Industrial and Employment Benefits Agreement
will highlight:
� Full and Fair
Opportunity
How manufacturers, consultants, contractors and service companies in
the Province will be given a full and fair opportunity to participate
on a competitive basis in the supply of goods and services used in any
proposed work or activity.
� First
Consideration � Procurement
How the purchasing practices of the Proponent will provide first
consideration for the procurement of services from within the Province
and for goods manufactured within the Province where these goods and
services are competitive in terms of fair market price, quality and
delivery.
� First
Consideration � Training and Employment
How individual residents in the Province will be given first
consideration for training and employment opportunities in the work
program.
� Supplier
Participation
That the Proponent will establish as soon as practical, Project
information centres in St. John's and Happy Valley-Goose Bay to keep
the general public informed about the Project. The centres will also
provide information relating to employment and supplier procurement
opportunities for all phases of the Project and be receiving points
for resumes and
tendering/bid documents.
The Proponent will also hold information sessions throughout the
Province regarding supplier participation programs.
� Engineering
That the Proponent will ensure that Project management, engineering,
procurement and Project service activities for the Project will be
carried out in the Province to the greatest extent possible. Such work
will be undertaken by, or have the significant participation of,
Newfoundland and Labrador based firms. When not available in the
Province, specialized expertise will be sourced and carried out
wherever available. In these instances, such firms from outside
the Province will be encouraged to involve Newfoundland and Labrador
engineering firms in these specialized engineering activities.
Further, the Proponent will provide a human resources plan outlining
participation by Newfoundland and Labrador engineers, geoscientists
and other technical disciplines, along with a plan indicating the
opportunities for them to develop and assume increasingly senior
positions as the Project proceeds.
�Newfoundland and
Labrador Construction/ Fabrication Facilities
That the Proponent will make full use of construction, fabrication and
assembly capabilities in the Province by requiring potential bidders
to bid the work using a qualified facility in the Province in their
bid where available. The Proponent will make potential bidders aware
of construction and fabrication facilities in the Province and the
Proponent will direct potential bidders to the appropriate Government
department/official for information on construction facilities and
capabilities in the Province.
Where construction, fabrication and assembly services are performed in
the Province, the Proponent will require contractors and
subcontractors carrying out that work to locate Project management,
fabrication engineering and procurement activity within the Province.
� Adjacency
Principle
That the Proponent will apply its adjacency principle policy to the
delivery of employment and business opportunities related to the
Project, in order to fulfil its commitment made during the
environmental assessment of the mine and mill/concentrator processing
plant.
� Air and Marine
Operations
That the Proponent will require the air operation company or companies
retained to provide air transportation for the Project and the
shipping company or companies retained to ship nickel/copper/cobalt
concentrates and finished nickel, and cobalt and copper reverts, to
have a base of operations in the Province and in the case of shipping
to destinations in Canada, that the vessels be Canadian flagged and
crewed and additionally
that the
nickel/copper/cobalt concentrate ships be crewed from within the
Province.
28. The Proponent will
develop and implement training initiatives for all phases of the Project
in co-operation with governments, aboriginal groups, labour
organizations, suppliers and training institutions in the Province.
These initiatives will include pre-employment and employment training
programs utilizing in-house and external training organizations
throughout the Province. Specific programs will be established for
training at the Voisey's Bay and Argentia sites. Maximum use will be
made of existing provincial education facilities near the Project sites.
Aboriginal Participation
29. The Proponent
acknowledges that the Labrador Inuit Association and Innu Nation assert
aboriginal rights and title to the Project area containing the nickel,
cobalt and copper deposits. The Proponent has negotiated and will enter
into Impacts and Benefits Agreements with both aboriginal groups. These
Agreements, when executed, will provide specific industrial and
employment opportunities for certain aboriginal groups residing adjacent
to the mine and mill/concentrator processing plant.
Project Employment
30. The Proponent will
implement a Project employment strategy that is consistent with the
Canadian Charter of Rights and Freedoms, ensures that individuals
resident in the Province are given first consideration for training and
employment opportunities associated with the Project, and recognizes the
adjacency principle referred to in paragraph 27.
Environmental Undertaking
Order
31. Subject to revisions
required to reflect the current scope of the Project, the Proponent will
abide by and implement the terms and conditions contained in the
Voisey's Bay Nickel Company Limited Mine and Mill Undertaking Order,
which are applicable to the mine and mill/concentrator processing plant.
Corporate Income Tax �
Newfoundland And Labrador
32. The Proponent will
reach an agreement with the Province on arrangements which, to the
extent permitted by law, will result in an allocation, for the purposes
of Part IV of the Federal Income Tax Regulations, of the
Proponent's gross revenues from the sale or disposition of
nickel/copper/cobalt products, whether in intermediate or final form,
from the Project to the Province.
Force Majeure
33. If the Proponent
establishes that it is prevented from performing any of its obligations
under the Statement of Principles by reason of one or more event(s) of
Force Majeure (as defined in Schedule A hereto), such obligations will
be suspended for the period during which the event(s) of Force Majeure
is/are in effect and the Proponent will be entitled to an extension of
any dates referred to in the Statement of Principles for a reasonable
period of time. However, even though the Proponent�s obligation(s)
will be suspended for the period of time during which the event(s) of
Force Majeure remain(s) in effect, when such event(s) of Force Majeure
is/are no longer in effect, the obligation(s) will become operative
until such obligation(s) are fulfilled.
UNDERTAKINGS BY GOVERNMENT
Aboriginal Agreements
34. The Government
acknowledges that the Labrador Inuit Association and Innu Nation assert
aboriginal rights and title to the Project area containing the mineral
deposits. The Government will enter into interim measures agreements or
other alternative agreements with both aboriginal groups that will
include the Voisey's Bay chapter of the respective land claims
agreements. The Government will also enter into an Environmental
Management Agreement with the Labrador Inuit Association and the Innu
Nation with respect to the Project. The Government will use its best
efforts to conclude negotiations on these agreements in a timely manner.
Electrical Rates and
Provision Of Power
35. The Government will
commit to cause Newfoundland and Labrador Hydro to charge the island
industrial electrical rate, or such lower electrical power rate that may
be offered from time to time to customers in comparable circumstances,
for the Proponent's processing facilities located on the island portion
of the Province and that a sufficient power supply will be available
when the commercial hydrometallurgical processing plant provided for in
paragraph 21 or other facility provided for in paragraph 22
commences operation.
Mining Lease
36. The Government will
issue a mining lease pursuant to the Mineral Act which will
provide, among other things, that the annual production of the mine will
be no more than 2.2 million tonnes of ore during the first 10 years of
mining operations and no more than 5.5 million tonnes of ore
thereafter and that primary processing will take place in the Province.
Exemption Orders
37. The Government will
issue an Exemption Order that will become effective upon the shipment of
first concentrate to the demonstration plant at Argentia. This Exemption
Order will allow the Proponent to ship out of the Province a fixed
volume of nickel/copper/cobalt concentrate containing a total of up to
355,000 tonnes of nickel from the date that the demonstration plant is
operational and ready to test nickel/copper/cobalt concentrate to the
date of the commencement of the commissioning and start up of the
hydrometallurgical processing plant at Argentia contemplated by
paragraph 21 or other facility contemplated by paragraph 22. This
Exemption Order will expire upon the Proponent reaching the volume limit
as set out in the Exemption Order.
This Exemption Order will provide that shipping of nickel/copper/cobalt
concentrate out of the Province will be suspended if (a) the Proponent
has not delivered to the Government the decision referred to in
paragraph 23 by December 31, 2008, or (b) the Proponent is not
proceeding diligently with the detailed engineering work for, and
construction of, the hydrometallurgical processing plant or other
facility thereafter for completion no later than December 31, 2011,
unless the Proponent�s failure to perform is by reason of one or more
event(s) of Force Majeure (as defined in Schedule A hereto). The
determination as to whether the Proponent is proceeding diligently will
be made annually on the anniversary date of the decision referred to in
paragraph 23 by a mutually acceptable independent licensed engineer
certifying whether the actual construction of the selected facility is
on schedule with the accepted implementation plan.
38. The Government will
also issue an Exemption Order allowing the Proponent to ship out of the
Province an additional fixed volume of nickel/copper/cobalt concentrate
containing a total of up to 85,000 tonnes of nickel, during the
commissioning and ramp up of the hydrometallurgical processing plant
contemplated by paragraph 21.
39. In the event that the
Proponent proceeds with the commercial hydrometallurgical nickel matte
processing facility or other facility provided for in paragraph 22, the
Government will issue an Exemption Order, which will become effective on
the date that such processing facility commences commissioning and
ramping up, that will allow the shipment of all nickel/copper/cobalt
concentrate from the Project out of the Province, subject to the
continued operation of the hydrometallurgical nickel matte processing
facility or other facility at an operating rate capable of processing
the amount of nickel contained in the nickel/copper/cobalt concentrate
produced by the Voisey�s Bay mill/concentrator processing plant.
This Exemption Order will
provide that shipping of nickel/copper/cobalt concentrate out of the
Province will be suspended during such period(s) that such facility is
not operating, unless it is not operating by reason of one or more
event(s) of Force Majeure (as defined in Schedule A hereto) or it is not
operating temporarily due to routine maintenance or vacation shutdown.
40. The Government,
through the issuance of an Exemption Order, will allow the
Proponent to ship out of the Province all copper concentrate produced
from the Project for the duration of the Project or until sufficient
copper reserves are discovered by the Proponent to permit commercial
processing in the Province. Should commercial processing of copper be
established in the Province by a third party, the Proponent will offer
for sale its available copper concentrate to such third party for its
facility on prevailing commercial terms and conditions subject to
availability and the Proponent�s existing contractual obligations.
Issuance
of Approvals
41. Where the Proponent
has submitted all information and data in compliance with applicable
legislation, regulatory provisions and policies required by the
Government for it to issue or grant necessary permits, authorizations,
orders and other approvals in accordance with the Statement of
Principles, the Government will issue or grant such permits,
authorizations, orders and other approvals on a timely basis.
If the Government does not issue or grant such permits, authorizations,
orders and other approvals on a timely basis, the Proponent will be
entitled to (a) an extension of any dates referred to in the Statement
of Principles for a reasonable period of time, and (b) an amendment to
the Exemption Order referred to in paragraph 37 to allow additional
amounts of nickel/copper/cobalt concentrate to be shipped out of the
Province, which amount will be calculated on the basis of the extension
referred to in clause (a) and provided that the Proponent establishes
that it will likely ship out of the Province the fixed volume of nickel
in such Exemption Order prior to the revised completion date of the
hydrometallurgical processing plant or other facility.
Legislative Framework
42. The Government
acknowledges that the Proponent is relying upon the good faith of the
Government to maintain substantially the legislative and regulatory
framework applicable to the Project as at the date of execution of the
Statement of Principles (the "Framework"), subject to
legislative amendments contemplated in the Statement of Principles and
legislation of general application. The Government will maintain the
Framework consistent with the Statement of Principles, subject to
governmental responsibilities, including responsibility for ensuring
proper management of the Province�s resources, the protection and
maintenance of public health and safety and the protection of the
environment. The Government acknowledges that the Statement of
Principles is consistent with current public law and governmental
responsibilities.
The Proponent acknowledges that the Government, in consideration of
agreeing to maintain the Framework, has relied upon the good faith of
the Proponent to carry out its undertakings as enumerated in the
Statement of Principles and its obligations to be contained in the
Binding Agreements.
Special Project Order
43. The Government will
issue a Special Project Order or Orders under the Labour Relations
Act to ensure a stable labour relations environment throughout the
construction phases of the Project. This Order or these Orders will
include, without limitation, such provisions as no strikes and lock-outs
and the ability to designate the union organization and employer's
representative that will be involved in collective bargaining.
Corporate Income Tax
44. The Government will
provide that the rate of provincial corporate income tax applicable to
the Proponent will be the lower of the "all provinces average"
or the provincial income tax rate.
45. The Government will
undertake to indemnify the Proponent for any double taxation resulting
from an agreement regarding the allocation of gross revenue for purposes
of Part IV of the Federal Income Tax Regulations.
Mining Taxes
46. The Government will
introduce and support legislation to amend the Mining and Mineral
Rights Tax Act (the "Act") and will undertake that the tax
rate, tax base, and tax credit provision in the amended Act will be no
more onerous to the Proponent than the following:
MINING TAX
Tax Rate
� 16% effective
rate
� 15% on 80% of
net income
� 20% of 20% of
net income less taxable royalties paid for the grant of the
right to engage in mining operations
Tax Base
� Gross revenue
(including hedging gains or losses related to mine output)
� Less:
� Reasonable
operating expenses directly attributable to mining and
processing
� Depreciation
� 25%
declining balance
� 100% for new
mine assets
� Pre-production
expenses over estimated mine life
� Exploration
expenses incurred in Province � carry forward indefinite
period
� Processing
allowance
� 8% of
milling and concentrating assets in the Province
� 15% of other
processing assets in the Province
� Maximum of
65% of net income before processing allowance
Tax Credits
� Provincial
corporate income tax paid in respect of mining income may be
used to reduce mining tax payable for the first 10 years of
operation. Maximum annual credit of $2 million.
Non-deductible
Expenses
� Income and
capital taxes
� Mining tax
� Professional
fees related to tax appeals
� Interest and
other costs of financing
� Donations
� Social and
recreational costs not incurred at a remote mine site
� Payments
made pursuant to an IBA
� Amounts in
excess of the actual cost of non-arm's length transactions
Approval by the House of Assembly of the
Province
47. The Proponent
acknowledges that the Government intends to submit the Statement of
Principles to the House of Assembly for its consideration and approval.
In the event such approval is not given, the Statement of Principles
will be void ab initio and neither the Proponent nor the
Government will be liable to the other for any loss, damage,
cost or claim whatsoever resulting therefrom. The Government
acknowledges that any delay in such approval could significantly affect
the timing and other aspects of the Proponent�s commitments under the
Statement of Principles, including those set forth in paragraph 12.
Choice of Law and Forum
48. The Government and
the Proponent acknowledge that (1) the Binding Agreements will be
governed by, and construed in accordance with, the laws of the Province
and the applicable laws of Canada, and (2) they will attorn to the
courts of the Province.
Statement of
Principles
Voisey�s Bay Project
Schedule A
1. For the purposes hereof:
"Person" includes any individual, partnership, limited
partnership, firm, trust, body corporate, unincorporated body of Persons
or association.
"Proponent" means collectively, Inco Limited, Voisey�s
Bay Nickel Company Limited, their respective affiliates as such term is
defined in the Corporations Act, and any Person which together with
any of them by way of partnership, joint venture, subcontract or otherwise
is an owner, operator or developer of the Project as defined in Paragraph
1 of the Statement of Principles.
"Processing Related Reason" means any situation where the
Proponent is unable to meet its obligations under paragraph 25 of the
Statement of Principles as a result of either (i) the unavailability, for
whatever bona fide reason, of concentrate or other form from any
external or other source, or (ii) the unavailability of concentrate or
other form from any external or other source on terms which are reasonable
commercial terms, including, without limitation, where the terms relating
to price or specifications would make it uneconomic or technically not
feasible for processing in order to meet the requirements of paragraph 25
of the Statement of Principles.
Subject to the exceptions
and qualifications below, "Force Majeure" means one or more of
the following events:
2. Subject to the exceptions and
qualifications below "Force Majeure" means one or more of the
following events:
(a) acts of God or natural
disasters, adverse weather conditions or other similar occurrences;
(b) acts of war (declared
or undeclared) or conditions arising out of or attributable to any
such acts of war, revolutions, insurrections, civil strife, formal or
informal hostilities, mob violence, riots and similar disturbances,
blockades or any other unlawful acts against public order or
authority;
(c) strikes, lockouts, work
stoppages or labour disturbances, unless directly and proximately
caused by an unlawful act or omission of the Proponent;
(d) delay or failure by
suppliers or transporters of materials, parts, supplies, services or
equipment; contractors� or sub-contractors� shortage of, or
inability to obtain, labour, transportation, materials, machinery,
equipment, supplies, utilities or services; or breakdown of equipment,
machinery or facilities, unless caused by or resulting from an
unlawful act or omission of the Proponent;
(e) accidents; and
(f) in respect of the
Proponent�s obligation in paragraph 25, a Processing Related Reason,
provided that, a Processing Related Reason will not be an event of
Force Majeure at any time after 3 years following the cessation of
mining operations for the Project.
In order to obtain relief for
one or more event(s) of Force Majeure under the Statement of Principles, the
Proponent will (a) use commercially reasonable efforts to (i) prevent the
occurrence of, (ii) perform its obligations in the face of, and (iii)
terminate such event of Force Majeure (other than the events described in
paragraph 2(c) of this Schedule A) relied upon; and (b) give notice of such
event as soon as reasonably practical.
2002 06
11
10:35 a.m.
|