Weekly Public Status Report
Oil and Gas Activities Offshore Newfoundland and Labrador
Issued: February 16, 1999
(Also available at: //www.cnopb.nfnet.com)

Drilling
Well / Location Installation Spud
Date
Current
Depth (Projected Total Depth)
Current
Operation
HMDC Hibernia B-16 4Z
46 45'02.6"N; Lat.
48 46'57.7"W: Long.
Licence: PL 1001
Hibernia Platform
M71 (East Rig)

November 22, 1997 4,825 M
(4,825 M)

Well workover
HMDC Hibernia B-16 11
46 45'02.1"N; Lat.
48 46'54.4"W: Long.
Licence: PL 1001
Hibernia Platform
M72 (West Rig)
September 20,
1998
8,485, M
(8,485 M)
Running 178 mm liner
Hebron D-94
46 33'00.7"N;Lat.
48 29'45.8"W; Long.
Licence: SDL1007
Glomar Grand Banks December 30, 1998 2,105 M
(2,105 M)
Preparing to test
Shoal Point K-39
48 38'25.3" N;Lat.
58 50'33.5" W;Long.
Licence:  EL 1021
Nabors 375ETD February 8, 1999 311 M
(3,200 M)
Drilling 444.5 mm hole

Production
Well Well Type Completion Date Status
HMDC- Hibernia B-16 1 Oil Producer December 2, 1997 Producing
HMDC- Hibernia B-16 2 Oil Producer December 19, 1997 Producing
HMDC - Hibernia B-16 3 Oil Producer February 24, 1998 Producing
HMDC - Hibernia B-16 5 Gas Injector August 5, 1998 Shut-in
HMDC - Hibernia B-16 6 Water Injector

June 29, 1998

Shut-in
HMDC - Hibernia B-16 7 Water Injector May 22, 1998 Injecting
HMDC - Hibernia B-16 9 Water Injector October 10, 1998 Injecting
HMDC - Hibernia B-16 10Z Gas Injector January 26, 1999 Shut-in

Contact: Canada-Newfoundland Offshore Petroleum Board, (709) 778-1400

________________________

Glossary of Petroleum Terminology

BOP/BOP Stack: Blowout preventers/blowout preventer stack - an assembly of heavy-duty valves attached to the wellhead to control well pressure and prevent a blowout.

Casing: Steel pipe set in a well to prevent the hole from sloughing or caving and to enable formations to be isolated (there may be several strings of casing in a well, one inside the other).

Cementing: Pumping a liquid slurry of cement, water and other additives behind a string of casing to isolate formations.

Completion/Completed::The activity necessary to prepare a well for the production of oil or gas or the injection of water or gas into the reservoir.

Fish: An object lost (or stuck) in the wellbore obstructing operations.

Fishing: Operations to recover fish.

Injecting: Injecting water or gas into the resevoir for the purpose of maintaining resevoir pressure, maximizing oil recovery and conserving resources.

Liner: A length of casing suspended from the base of a previously installed casing string (a liner does not extend back to the surface of the well).

Logging: Acquisition of downhole data using tools run in the well, usually on wireline.

Perforate/Perforating: Piercing the casing and cement using shaped explosive charges to provide a  flow path for formation fluids

Producing/Production: Flowing oil and/or gas from a well to the production systems.

Production tree: An arrangement of heavy duty valves and fittings installed on the wellhead to control flow from the well and/or to facilitate injection operations.

Reaming: An operation to restore a wellbore to its original diameter (occasionally, a wellbore will cave in).

Shut-in: A well in which the valves in the production tree have been closed to cease production or injection operation on a well.

Sidetracking: The operation of deviating a well around a fish.

Spud: The initial penetration of the ground or seafloor - the start of the drilling operation.

Suspension/Suspend: The temporary cessation of drilling or production operations in a well.

Well workover:  A program of work performed on an existing well.

Wellbore: The hole drilled by the drill bit.

Wellhead: Steel equipment installed at the surface of the well containing an assembly of heavy duty hangars and seals (the wellhead is used to support the weight of casing strings hung from it and to contain well pressure).

1999 02 16 3:15 p.m.