February 28, 1997
(Environment and Labour)


Environmental assessment bulletin

Environment and Labour Minister Kevin Aylward has announced the following events relative to the Environmental Assessment Act. In the case of documents received or approved, copies may be obtained by contacting the regional office of the Department of Environment and Labour or by calling toll-free 1-800-563-6181. Comments on submitted documents are invited from the public, addressed in writing to the minister, and are welcome prior to the deadline date following each item.

  • NEW UNDERTAKINGS REGISTERED:

    Island Pond Hydroelectric Development (Resubmission)
    Proponent: Newfoundland and Labrador Hydro

The proponent proposes to construct and operate a 36 megawatt (MW) hydroelectric development and associated 230 kilovolt (kV) transmission line of approximately 40 km. The proposed Island Pond Development will utilize the flow from Meelpaeg Reservoir to develop the 25 m head which exists between the Reservoir and Crooked Lake. The development will include a 3,000 m diversion canal between Meelpaeg Reservoir and Island Pond, 750 m forebay canal, dam, intake, penstock, powerhouse and transmission line. The permanent access road will run from North Salmon Dam road via the Ebbegunbaeg control structure. Construction is tentatively scheduled to begin in the fall of 1999 for the transmission line and the summer of 1998 for the major civil works and roads. The project was previously registered on March 31, 1987 and an Environmental Impact Statement (EIS) was required. The EIS was completed and received ministerial approval on September 23, 1993. The project was not initiated within three years of the date of release and re-registration is required as per Section 10 (8) of the Environmental Assessment Regulations.

  • Grand Falls Turbine Generator - Beeton Unit
    Proponent: Abitibi-Price (Grand Falls Division)

The proponent proposes to construct a new penstock and powerhouse extension on the Exploits River. This work is part of an ongoing major rehabilitation program for the existing hydroelectric facilities which have operated since the early 1900s. The hydroelectric facilities at Grand Falls consisted of eight generators until the late eighties. At present, the operation consists of units 5,6,7, and 8 which are four MW each and unit 4 which is 28 MW. A new 30 MW turbine/generator (Beeton Unit) will be installed in the powerhouse extension. Construction is tentatively scheduled to begin in April, 1998 and continue for approximately 24 months.

  • Cape Bonavista Wind Power Project
    Proponent: Tacke Windpower Inc.

The proponent proposes to construct and operate a 15 MW Wind Farm utilizing 25 wind turbines of 600 kW each, to be located on Cape Bonavista near the Town of Bonavista. The wind turbines are horizontal axis, three bladed wind energy converters with a maximum hub height of 50 metres. The rotor diameter will be 43 metres. Connection to the power system is required near the terminus of the 138 kV Newfoundland Power transmission line to Bonavista. Each turbine row will have a five metre wide gravel access road. Electrical service within the turbine rows is installed underground. Construction is tentatively scheduled to take six-seven months with the earliest in-service date of November 1998.

  • Grates Cove Wind Power Project
    Proponent: Tacke Windpower Inc.

The proponent proposes to construct and operate a 15 MW Wind Farm utilizing 25 wind turbines of 600 kW each, to be located on the Bay de Verde Peninsula near Grates Cove. The wind turbines are horizontal axis, three bladed wind energy converters with a maximum hub height of 50 metres. The rotor diameter will be 43 metres. Connection to the power system will be at the Tanks Transformer Station located near Old Perlican. A 66 kV feeder terminates at that point. Each turbine row will have a five metre wide gravel access road. Electrical service within the turbine rows is installed underground. Construction is tentatively scheduled to take six - seven months with the earliest in- service date of November 1998.

  • Elliston Region Wind Power Project
    Proponent: Tacke Windpower Inc.

The proponent proposes to construct and operate a 15 MW Wind Farm utilizing 25 wind turbines of 600 kW each, to be located on Green and Burnt Ridges near the town of Bonavista. The wind turbines are horizontal axis, three bladed wind energy converters with a maximum hub height of 50 metres. The rotor diameter will be 43 metres. Connection to the power system is required near the terminus of the 138 kV Newfoundland Power transmission line to Bonavista. Each turbine row will have a five metre wide gravel access road. Electrical service within the turbine rows is installed underground. Construction is tentatively scheduled to take six - seven months with the earliest in- service date of November 1998.

  • Argentia Cogeneration Power Project
    Proponent: Sithe Canadian Holdings Inc.

The proponent proposes to construct and operate a 185 megawatt oil- fuelled cogeneration facility to be located adjacent to the proposed Voisey's Bay Nickel Company Ltd. smelter/refinery at Argentia. The proposed development will use three 40 MW turbine generators, three heat recovery steam generators and a single large steam turbine. The facility will utilize approximately 12 to 15 acres of land. The proposed project is designed to operate for 30 years. Construction is tentatively scheduled to take 20 to 22 months.

  • Port Harmon Cogeneration Project
    Proponent: Abitibi - Price Inc.

The proponent proposes to construct and operate a 35 MW cogeneration facility at its Stephenville Paper Mill at the Harmon Complex Industrial Park. The undertaking will supply 35 MW of power to the provincial grid and provide 110,000 - 160,000 pounds per hour of steam for the plant processes. The proponent proposes to install two oil-fuelled package boilers and a turbine generator. The new boilers would reduce the need for #6 fuel oil in the power boiler. The cogeneration facility will be housed within the existing structures at the mill complex. Construcition is tentatively scheduled to begin in April 1999.

  • Sheffield Lake Hydroelectric Development
    Proponent: Deer Lake Power Company Ltd.

The proponent proposes to construct and operate a five MW "run-of- river" hydroelectric generating station located at Sheffield Lake. The proposed development will include a dam and spillway at the outlet of Sheffield Lake, a 1,900 metre penstock and a surface powerhouse located on the shore of Birchy Lake. A 138 kilovolt (kV) transmission line will deliver energy to the transmission line adjacent to the Trans Canada Highway. Construction is tentativley scheduled to begin in mid 1998.

  • Argentia Multiple Gas Turbine (GTS) Power Project
    Proponent: Duke Energy Corporation

The proponent proposes to construct and operate a 200 megawatt combined cycle gas turbine and steam turbine generator. The plant will be designed to operate with light fuel oil. The project will be located adjacent to the Voisey's Bay Nickel Company Smelter/Refinery. The major power building will be a pre-engineered metal building. A tank farm will be constructed and will provide approximately 60 days of fuel storage. Construction is tentatively scheduled to begin in early 1998.

  • Southwest River (Phase 2) Small Hydro Development
    Proponent: Frontier Hydro Development Limited

The proponent proposes to construct and operate a two MW "run-of- river" small hydro-electric generating station on the Southwest River near Port Blanford. The undertaking will include the construction of a small concrete gravity dam/spillway, intake structure, penstock, powerhouse and transmission line. Access to the project will entail the upgrading of the existing access road. Construction is tentatively scheduled to begin in the fall of 1998.

  • Come By Chance Cogeneration Power Project
    Proponent: North Atlantic Refining Limited

The proponent proposes to produce 205 MW of electric power through the gasification of refinery bottoms to synthetic gas in an Integrated Gasification Combined Cycle (IGCC) plant. The proposed process will use heavy oil produced at the refinery (refinery fuel oil bottoms) in a state-of-the-art technology to produce a clean, sulphur-free gas that will be burned in the IGCC plant's gas turbine driving the electric power generator. The plant will include, an air separation unit, charge holding unit, gasifiers, carbon extraction unit, low temperature gas cooling unit, an acid gas removal unit, sulphur recovery unit, tail gas recovery unit, boiler feed water preparation, air separation unit, effluent water pretreatment, process control room, building to house a turbine and power generator, access road, transmission line, modifications to the existing electrical substation, and associated pipelines. The proposed location is immediately adjacent to the refinery. Construction is tentatively scheduled to begin in July of 1998 and require 56 weeks.

  • St. John's Southside Thermal Plant Repowering Project
    Proponent: Newfoundland Light and Power Co. Ltd.

The proponent proposes to repower its St. John's Southside Thermal Plant to generate 72.6 MW of power. The project consists of replacing the existing boilers with a combination of equipment including gas turbine generator and a heat recovery steam generator. This plant was originally established in 1956 and had a design capacity of 30 MW. Construction is tentatively scheduled to begin early in 1998.

  • Green Island Lake Cottage Development Plan
    Proponent: Department of Government Services and Lands

The proponent proposes to allocate 95 cottage lots in three designated areas near the community of Flower's Cove. The cottage areas surround Eastern Lake, Green Island Lake and two small ponds lying to the north. The lots will not be accessible by road. The allocation of the lots will be carried out by the Lands Branch tentatively in the spring of 1997.

The public is invited to examine these registration documents and offer written comment to the minister on whether an Environmental Impact Statement (EIS) should be ordered. The deadline for the receipt of public comments is March 30, 1997.

  • CORRECTION NOTICE:

    Paddy's Pond Commercial Airstrip
    Proponent: Private Aircraft Association of Newfoundland and Labrador

In the February 13, 1997, Environmental Assessment Bulletin it was incorrectly stated that Roger Pottle was the contact for purposes of environmental assessment for the project. The contact person for the project is: Wayne T. Grimes (709) 437-1062.

  • ADDITIONAL REVISIONS TO ENVIRONMENTAL PREVIEW REPORT

    Garia Bay (Northwest Brook) Hydroelectric Development
    Proponent: Genergy Inc. - Project Manager on behalf of Penny Hydro Inc.

The first draft of the Environmental Preview Report (EPR) has been reviewed and additional revisions are required.

  • NO ENVIRONMENTAL ASSESSMENT REQUIRED

The minister has decided that an environmental impact statement is not required for the following undertakings which have recently been registered and examined by government and the public. The undertakings are released subject to other regulatory and permitting requirements.

- Newville Automobile Salvage Yard

- Star Lake Hydroelectric Project Dam Re-Alignment

A guide to the Environmental Assessment Process is available from the Department of Environment and Labour. The minister encourages all interested parties to become involved and to make comments known. Further information may be obtained by contacting the Director of Environmental Assessment at (709) 729-2562, or toll-free: 1-800-563-6181 or by mail to:

Director, Environmental Assessment Division
Department of Environment and Labour
West Block, Confederation Building
P.O. Box 8700
St. John's, NF
A1B 4J6

Environmental Assessment News Releases are on the Internet //www.gov.nl.ca/envlab/env_news.htm

1997 02 28 5:20 p.m.
 

SearchHomeBack to GovernmentContact Us


All material copyright the Government of Newfoundland and Labrador. No unauthorized copying or redeployment permitted. The Government assumes no responsibility for the accuracy of any material deployed on an unauthorized server.
Disclaimer/Copyright/Privacy Statement